Stages of a construction case
Every case moves through stages; the stage shows how close a project is to becoming a building. Here is what each stage means and the order they usually come in.
-
Prior information request
Prior information request: the developer asks the council what may be built, before filing a project.
Council reply: 15–45 working days by complexity; silence counts as approval.
-
Under licensing
Project filed; the council is reviewing it.
Completeness ~20, architecture ~30, decision ~20–45 working days (legal limit).
-
Architecture approved
Architecture approved; specialties and the permit come next.
Architecture accepted; specialties and the permit follow.
-
Permit issued
Permit (alvará) issued: building may start.
Permit (alvará) issued — building may start.
-
Prior communication
Prior communication: a simpler route, without a full licence.
No waiting period: works start after paying the fees.
Timelines vary widely — from months to years. The law sets deadlines for the council to reply, but the real time depends on the project, the specialties and the council itself. Issuing a permit does not guarantee the works go ahead.